Deepak Kumar Pandey
About Me
Employment Records
S No. Description. Particulars.
1. Duration From April 2014 onwards
Organization Ramayana Realtors Pvt. Ltd. & Sister Concerns.
Position Head – Project’s
Project Development of Infrastructure & Horizontal as well Vertical
developments of Villas & Multistory ( Commercial / Residential) on 552 Acres Land
Project cost Rs.784 Cr PTO
Responsibility Controlling entire site, Consulting and Coordinating with Contractors,
Co-ordinate with Architect for updates in drawing and design, Consult
With site engineers for development update.
2. Duration From April 2013 to March 2014
Organization TATA Projects Ltd., Hyderabad
Position Manger – Construction
Project EDFCCIL Project (Railways) at Kanpur, U.P.
Project cost Rs 1370 Cr
Responsibility Entire Managing & Execution of the Project.
3 Duration From 2011 to 2013
Organization IVRCL Ltd. Hyderabad
Position Sr. Project Manager
Project NTPC STPP I /c OHP Work at RIHAND,U.P. & MOUDA,NAGPUR
Project cost Rs. 900 Cr
Responsibility Entire Execution of the Project.
4. Duration From 2010 to 2011
Organization Reacon Engineers I. Pvt. Ltd. Kolkata
Position Project Head
Project OHP, STPP WORK at Bhilai Steel Plant, Bhilai
Project cost 230 Cr
Responsibility Handling to deliver the project in all respect.
5. Duration From Jan 2010 to Aug 2010
Organization Era Infra & Engg. Ltd., New Delhi
Position Project Manager
Project Construction of Capitol Complex – HOD Buildings, Naya Raipur
Project cost Rs. 208.94 Cr
Responsibility Entire Execution I /c Quality control, Procurement of material and
Manpower.
6. Duration From 2007 to 2009
Organization Babylon Group Raipur
Position Project in Charge
Project 5 Star Hotel in Raipur
Responsibility To look after total work i/c structural as well as finishing.
Project Cost Rs 100 Cr
7. Duration From 2004 to 2007
Organization Rituraj Steel Pvt. Ltd., Bilaspur (C.G.)
Position Project in Charge
Project Multi Story Mega Shopping Mall, 4 Star Hotel & Residential
Apartments
Project cost Rs. 75 Cr
Responsibility Entire Execution work
8. Duration From 1999 to 2004
Organization Shri Ram Constructions, Raipur (C.G.)
Position Project Manager
Project Mega Multi Storied Public Buildings & National Highway,
Culverts/Minor Bridges & Road Signage’s & Retro Refractive
Road Marking work
Project cost Rs. 60 Cr
Responsibility Entire work to hand over the project. PTO
9. Duration From 1997 to 1999
Organization Bhilai Builders, Bhilai (C.G.)
Position Project in Charge
Project Mega Residential & Multi Storied Commercial Projects
Project cost Rs. 30 Cr
Responsibility Complete execution of the project with entire planning, quality control
& procurement of material and manpower.
10. Duration From 1995 to 1997
Organization Century Cement, Baikunth,
Position Project Engineer
Project Captive Thermal Power Plant & other Plant units
Project cost Rs. 25 Cr
Responsibility Execution of Civil Work.
11. Duration From 1994 to 1995
Organization Vimal Constructions , Raipur
Position Site Engineer
Project Steel Plant & Textile Plant different units
Project cost Rs. 15 Cr
Responsibility Execution of Civil Work.
12. Duration From 1992 to 1994
Organization Vartika Constructions Pvt. Ltd., Raipur
Position Project In Charge
Project Mega Housing Project
Project cost Rs. 05 Cr
Responsibility Entire Execution with complete management to project delivery.